Introduction Images of 150 years DEME, ending with a view on hashtag #DEME150.

Discover 150 years of DEME!

In 2026, DEME celebrates 150 years of marine and environmental engineering. From our early roots in 1876, we have grown from our origins in dredging and marine works into a leading, diversified group - shaped by expertise, innovation, resilience and a constant drive to push boundaries. 

Throughout this anniversary year, we’ll take you on a journey through our history, sharing stories and moments that show how challenges were approached, solutions were developed and ambitions kept moving forward. Across our channels and on this dedicated anniversary website, you can discover the people, projects and breakthroughs that made DEME what it is today. This website will be updated weekly with new stories. Throughout the year, we will use #DEME150 to share and connect these stories. 

As we reflect on 150 years, we continue to look ahead with the same spirit that defines us: We Care. We Dare. We Deliver.

1988

Laying the groundwork for the Channel Tunnel

When the Channel Tunnel officially opened on May 6, 1994, connecting the United Kingdom and France beneath the English Channel, it marked the realization of a centuries-old dream. Few people know, however, that Flemish companies including DEME played a role long before the first trains began running.

In 1988, Hydro Soil Services (HSS), a joint venture between Dredging International and Smet Boring, was among the first contractors active on the British side of the project. Working for the TransManche Link consortium, HSS helped prepare the site at the foot of the iconic Shakespeare Cliff near Dover, where one of the largest infrastructure projects of the twentieth century was taking shape.

A key part of the assignment was the construction of an artificial peninsula that would receive millions of cubic meters of material excavated from the three tunnel bores. To execute the works, HSS deployed its self-elevating platform Tijl II, while Dredging International sent the backhoe dredger Zenne to support the operation. Together, they helped create a series of lagoons behind a double sheet-pile wall extending more than two kilometers along the coast.

The project was far from straightforward. The exposed coastline near Dover is notorious for severe southwesterly storms, making the installation of the sheet-pile walls and the positioning of equipment a challenging undertaking. Yet the work was completed successfully, demonstrating the expertise and ingenuity that would become hallmarks of DEME projects around the world.

While the Channel Tunnel itself was built by an international consortium, Dredging International and HSS were there from the very beginning, helping lay the groundwork for what would become one of Europe's most iconic engineering achievements.

Disclaimer

With 150 years of history, there are countless moments to tell. In this anniversary year, we share a non-exhaustive selection of stories that illustrate how DEME became the company it is today. These stories are drawn from a variety of historical sources, including books by authors such as Dirk Podevijn and Mon Vanderosteyne, company publications and the input of colleagues across the organization. As this website looks back on 150 years of heritage, it features archival material from different eras. Safety standards and working practices have evolved significantly over time and should be understood in their historical context.